St Pauls Way
Duration
40 Weeks
Subcontract Value
£2.405m
Location
Bow
Description of Works:
Project consisted of 3 Phases, A-D, E-F & a school.
Woodhurst Construction were employed to undertake labour and all materials bar brickworks & masonry support including but not limited to supply of all sundry materials, including insulation, fire barriers, masonry support etc.
The project was completed in 40 weeks, to the clients programme.
Works comprised a mixture of 1, 2 & 3 bedroom flats, with garden walls and feature areas, all completed to a high quality and standard. Also comprised a school area which required a fast turn around of 4 weeks.